| Residents’ tug-of-war stalls subway by railgenie on 29 August, 2012 - 03:00 PM | ||
|---|---|---|
railgenie | Residents’ tug-of-war stalls subway on 29 August, 2012 - 03:00 PM | |
Months after the completion of work on the Radha Nagar subway in Chromepet by the Southern Railway, the Highways Department has not been able to take up its portion of the work due to the changing of stance of the residents in the area.The box portion of the structure beneath the railway tracks near the Chromepet station has been completed and barricades placed. But the Highways, which has to take up work to connect both sides, is unable to do so as the residents have changed their mind yet again though land acquisition has been completed. There are also differences between residents in the immediate vicinity whose lands have been acquired for the project and those in surrounding areas.The former now want the subway to be converted to a pedestrian facility, which was how the original proposal in 2000 by the two departments to replace Level crossing 27 intended it to be. But many residents, especially those in surrounding areas, objected to the proposal and wanted a vehicular subway and the Municipality too passed a resolution accordingly. The design was changed and the Railways constructed a box accordingly. However, residents whose houses will be affected, are now demanding the proposal be given up.“It is not possible to change the design of the subway as the box structure has been constructed already. To minimise land acquisition, the width of the service lanes has been reduced,” said a source in the Highways Department. | ||