56319 Nagercoil-Coimbatore Passenger will be 1 hr late for 88 days by RailEnquiry Admin on 18 November, 2016 - 06:53 PM | ||
---|---|---|
RailEnquiry Admin | 56319 Nagercoil-Coimbatore Passenger will be 1 hr late for 88 days on 18 November, 2016 - 06:53 PM | |
Due to maintenance work between Thirumangalam and Virudhunagar under Madurai division - 56319 Nagercoil-Coimbatore Passenger will arrive Coimbatore at least one hour late. Track maintenance work will be carried out for 88 days between Virudhunagar and Thirumangalam till February 2. The passenger train will arrive at 09:50PM at Coimbatore, while at Dindigul it will arrive by 03:25PM. The scheduled time of arrival at Dindigul is 02:25PM. Enroute one hour delay will be applicable on every stoppage. |